·North Yorkshire Council is working in Partnership with Sherburn Town Council to improve the public realm along the East Side of Low Street.
· The work consists of upgrading all surfacing using higher quality materials and adding brand-new town centre map and real time bus information and new seating. The project aims to achieve a higher quality town centre.
· The areas we are improving are from the Swan Pub down to Starkey’s Butchers.
· The project is funded through Programme for Growth through Selby District Council and Shared Prosperity Funding.
· The project will start on site on Monday 24th February and the work is due for completion on Friday 8th August 2025.
· The work will be completed in phases to minimise disruption in the town.
Details of the work can be accessed via the links. Copies will also be added to the notice board next to Tesco, the Eversley Park Centre and the library.

Proposed
Site and Block Plan
Site Contacts
Karl Marlow - Project Manager Align karl.marlow@alignpropertypartners.co.uk
Available on 01609 797320 Monday, Tuesday & Thursday 8.30pm - 4pm
Jamie Kerman - Site Manager for PBS Construction.